Data Format

Input Data Format

Instances are specified by JSON files containing the following main sections:

Each section is described in detail below. See case118/2017-01-01.json.gz for a complete example.

Parameters

This section describes system-wide parameters, such as power balance penalty, and optimization parameters, such as the length of the planning horizon and the time.

KeyDescriptionDefaultTime series?
VersionVersion of UnitCommitment.jl this file was written for. Required to ensure that the file remains readable in future versions of the package. If you are following this page to construct the file, this field should equal 0.3.RequiredN
Time horizon (h)Length of the planning horizon (in hours).RequiredN
Time step (min)Length of each time step (in minutes). Must be a divisor of 60 (e.g. 60, 30, 20, 15, etc).60N
Power balance penalty ($/MW)Penalty for system-wide shortage or surplus in production (in /MW). This is charged per time step. For example, if there is a shortage of 1 MW for three time steps, three times this amount will be charged.1000.0Y

Example

{
    "Parameters": {
        "Version": "0.3",
        "Time horizon (h)": 4,
        "Power balance penalty ($/MW)": 1000.0
    }
}

Buses

This section describes the characteristics of each bus in the system.

KeyDescriptionDefaultTime series?
Load (MW)Fixed load connected to the bus (in MW).RequiredY

Example

{
    "Buses": {
        "b1": {
            "Load (MW)": 0.0
        },
        "b2": {
            "Load (MW)": [
                26.01527,
                24.46212,
                23.29725,
                22.90897
            ]
        }
    }
}

Generators

This section describes all generators in the system, including thermal units, renewable units and virtual units.

KeyDescriptionDefaultTime series?
BusIdentifier of the bus where this generator is located (string).RequiredN
Production cost curve (MW) and Production cost curve ($)Parameters describing the piecewise-linear production costs. See below for more details.RequiredY
Startup costs ($) and Startup delays (h)Parameters describing how much it costs to start the generator after it has been shut down for a certain amount of time. If Startup costs ($) and Startup delays (h) are set to [300.0, 400.0] and [1, 4], for example, and the generator is shut down at time 00:00 (h:min), then it costs $300 to start up the generator at any time between 01:00 and 03:59, and $400 to start the generator at time 04:00 or any time after that. The number of startup cost points is unlimited, and may be different for each generator. Startup delays must be strictly increasing and the first entry must equal Minimum downtime (h).[0.0] and [1]N
Minimum uptime (h)Minimum amount of time the generator must stay operational after starting up (in hours). For example, if the generator starts up at time 00:00 (h:min) and Minimum uptime (h) is set to 4, then the generator can only shut down at time 04:00.1N
Minimum downtime (h)Minimum amount of time the generator must stay offline after shutting down (in hours). For example, if the generator shuts down at time 00:00 (h:min) and Minimum downtime (h) is set to 4, then the generator can only start producing power again at time 04:00.1N
Ramp up limit (MW)Maximum increase in production from one time step to the next (in MW). For example, if the generator is producing 100 MW at time step 1 and if this parameter is set to 40 MW, then the generator will produce at most 140 MW at time step 2.+infN
Ramp down limit (MW)Maximum decrease in production from one time step to the next (in MW). For example, if the generator is producing 100 MW at time step 1 and this parameter is set to 40 MW, then the generator will produce at least 60 MW at time step 2.+infN
Startup limit (MW)Maximum amount of power a generator can produce immediately after starting up (in MW). For example, if Startup limit (MW) is set to 100 MW and the unit is off at time step 1, then it may produce at most 100 MW at time step 2.+infN
Shutdown limit (MW)Maximum amount of power a generator can produce immediately before shutting down (in MW). Specifically, the generator can only shut down at time step t+1 if its production at time step t is below this limit.+infN
Initial status (h)If set to a positive number, indicates the amount of time (in hours) the generator has been on at the beginning of the simulation, and if set to a negative number, the amount of time the generator has been off. For example, if Initial status (h) is -2, this means that the generator was off since -02:00 (h:min). The simulation starts at time 00:00. If Initial status (h) is 3, this means that the generator was on since -03:00. A value of zero is not acceptable.RequiredN
Initial power (MW)Amount of power the generator at time step -1, immediately before the planning horizon starts.RequiredN
Must run?If true, the generator should be committed, even if that is not economical (Boolean).falseY
Reserve eligibilityList of reserve products this generator is eligibe to provide. By default, the generator is not eligible to provide any reserves.[]N

Production costs and limits

Production costs are represented as piecewise-linear curves. Figure 1 shows an example cost curve with three segments, where it costs $1400, $1600, $2200 and $2400 to generate, respectively, 100, 110, 130 and 135 MW of power. To model this generator, Production cost curve (MW) should be set to [100, 110, 130, 135], and Production cost curve ($) should be set to [1400, 1600, 2200, 2400]. Note that this curve also specifies the production limits. Specifically, the first point identifies the minimum power output when the unit is operational, while the last point identifies the maximum power output.

Figure 1. Piecewise-linear production cost curve.

Additional remarks:

  • For time-dependent production limits or time-dependent production costs, the usage of nested arrays is allowed. For example, if Production cost curve (MW) is set to [5.0, [10.0, 12.0, 15.0, 20.0]], then the unit may generate at most 10, 12, 15 and 20 MW of power during time steps 1, 2, 3 and 4, respectively. The minimum output for all time periods is fixed to at 5 MW.
  • There is no limit to the number of piecewise-linear segments, and different generators may have a different number of segments.
  • If Production cost curve (MW) and Production cost curve ($) both contain a single element, then the generator must produce exactly that amount of power when operational. To specify that the generator may produce any amount of power up to a certain limit P, the parameter Production cost curve (MW) should be set to [0, P].
  • Production cost curves must be convex.

Example

{
    "Generators": {
        "gen1": {
            "Bus": "b1",
            "Production cost curve (MW)": [100.0, 110.0, 130.0, 135.0],
            "Production cost curve ($)": [1400.0, 1600.0, 2200.0, 2400.0],
            "Startup costs ($)": [300.0, 400.0],
            "Startup delays (h)": [1, 4],
            "Ramp up limit (MW)": 232.68,
            "Ramp down limit (MW)": 232.68,
            "Startup limit (MW)": 232.68,
            "Shutdown limit (MW)": 232.68,
            "Minimum downtime (h)": 4,
            "Minimum uptime (h)": 4,
            "Initial status (h)": 12,
            "Must run?": false,
            "Reserve eligibility": ["r1"],
        },
        "gen2": {
            "Bus": "b5",
            "Production cost curve (MW)": [0.0, [10.0, 8.0, 0.0, 3.0]],
            "Production cost curve ($)": [0.0, 0.0],
            "Reserve eligibility": ["r1", "r2"],
        }
    }
}

Price-sensitive loads

This section describes components in the system which may increase or reduce their energy consumption according to the energy prices. Fixed loads (as described in the buses section) are always served, regardless of the price, unless there is significant congestion in the system or insufficient production capacity. Price-sensitive loads, on the other hand, are only served if it is economical to do so.

KeyDescriptionDefaultTime series?
BusBus where the load is located. Multiple price-sensitive loads may be placed at the same bus.RequiredN
Revenue ($/MW)Revenue obtained for serving each MW of power to this load.RequiredY
Demand (MW)Maximum amount of power required by this load. Any amount lower than this may be served.RequiredY

Example

{
    "Price-sensitive loads": {
        "p1": {
            "Bus": "b3",
            "Revenue ($/MW)": 23.0,
            "Demand (MW)": 50.0
        }
    }
}

Transmission lines

This section describes the characteristics of transmission system, such as its topology and the susceptance of each transmission line.

KeyDescriptionDefaultTime series?
Source busIdentifier of the bus where the transmission line originates.RequiredN
Target busIdentifier of the bus where the transmission line reaches.RequiredN
Reactance (ohms)Reactance of the transmission line (in ohms).RequiredN
Susceptance (S)Susceptance of the transmission line (in siemens).RequiredN
Normal flow limit (MW)Maximum amount of power (in MW) allowed to flow through the line when the system is in its regular, fully-operational state.+infY
Emergency flow limit (MW)Maximum amount of power (in MW) allowed to flow through the line when the system is in degraded state (for example, after the failure of another transmission line).+infY
Flow limit penalty ($/MW)Penalty for violating the flow limits of the transmission line (in /MW). This is charged per time step. For example, if there is a thermal violation of 1 MW for three time steps, then three times this amount will be charged.5000.0Y

Example

{
    "Transmission lines": {
        "l1": {
            "Source bus": "b1",
            "Target bus": "b2",
            "Reactance (ohms)": 0.05917,
            "Susceptance (S)": 29.49686,
            "Normal flow limit (MW)": 15000.0,
            "Emergency flow limit (MW)": 20000.0,
            "Flow limit penalty ($/MW)": 5000.0
        }
    }
}

Reserves

This section describes the hourly amount of reserves required.

KeyDescriptionDefaultTime series?
TypeType of reserve product. Must be either "spinning" or "flexiramp".RequiredN
Amount (MW)Amount of reserves required.RequiredY
Shortfall penalty ($/MW)Penalty for shortage in meeting the reserve requirements (in /MW). This is charged per time step. Negative value implies reserve constraints must always be satisfied.-1Y

Example 1

{
    "Reserves": {
        "r1": {
            "Type": "spinning",
            "Amount (MW)": [
                57.30552,
                53.88429,
                51.31838,
                50.46307
            ],
            "Shortfall penalty ($/MW)": 5.0
        },
        "r2": {
            "Type": "flexiramp",
            "Amount (MW)": [
                20.31042,
                23.65273,
                27.41784,
                25.34057
            ],
        }
    }
}

Contingencies

This section describes credible contingency scenarios in the optimization, such as the loss of a transmission line or generator.

KeyDescriptionDefault
Affected generatorsList of generators affected by this contingency. May be omitted if no generators are affected.[]
Affected linesList of transmission lines affected by this contingency. May be omitted if no lines are affected.[]

Example

{
    "Contingencies": {
        "c1": {
            "Affected lines": ["l1", "l2", "l3"],
            "Affected generators": ["g1"]
        },
        "c2": {
            "Affected lines": ["l4"]
        },
    }
}

Additional remarks

Time series parameters

Many numerical properties in the JSON file can be specified either as a single floating point number if they are time-independent, or as an array containing exactly T elements, if they are time-dependent, where T is the number of time steps in the planning horizon. For example, both formats below are valid when T=3:

{
    "Load (MW)": 800.0,
    "Load (MW)": [800.0, 850.0, 730.0]
}

The value T depends on both Time horizon (h) and Time step (min), as the table below illustrates.

Time horizon (h)Time step (min)T
246024
241596
245288
366036
3615144
365432

Output Data Format

The output data format is also JSON-based, but it is not currently documented since we expect it to change significantly in a future version of the package.

Current limitations

  • Network topology remains the same for all time periods
  • Only N-1 transmission contingencies are supported. Generator contingencies are not currently supported.
  • Time-varying minimum production amounts are not currently compatible with ramp/startup/shutdown limits.
  • Flexible ramping products can only be acquired under the WanHob2016 formulation, which does not support spinning reserves.